Ronald Street, North Coburg – Road Reconstruction Works
Project Overview
In 2019 – 20 Council reconstructed Ronald Street, North Coburg between Ballard Avenue and Danthonia Street.
The works comprised:
- Construction of new underground drainage system and pits
- Reconstructing the existing concrete kerb and channel
- Reconstructing the existing road pavement
- Laying of a new asphalt road surface
- Reconstruction of vehicle crossings between new kerb and footpath edge
- Reinstatement of nature strips
- Total length 295m
Budget and Timelines
- Budget $370,000
- Construction Start Date: July 2019
- Construction End Date: October 2019