Ronald Street, North Coburg – Road Reconstruction Works

Project Overview

In 2019 – 20 Council reconstructed Ronald Street, North Coburg between Ballard Avenue and Danthonia Street.

The works comprised:

  • Construction of new underground drainage system and pits
  • Reconstructing the existing concrete kerb and channel
  • Reconstructing the existing road pavement
  • Laying of a new asphalt road surface
  • Reconstruction of vehicle crossings between new kerb and footpath edge
  • Reinstatement of nature strips
  • Total length 295m

Budget and Timelines

  • Budget $370,000
  • Construction Start Date:  July 2019
  • Construction End Date:  October 2019

ronald street