Lorensen Avenue, Coburg North – Road Reconstruction Works
Project Overview
In 2019 – 20 Council reconstructed Lorensen Avenue, Coburg to the north of Orvieto Street.
The works comprised:
- Construction of new underground drainage system and pits
- Reconstructing the existing concrete kerb and channel
- Reconstructing the existing road pavement
- Laying of new asphalt road surface
- Reconstruction of vehicle crossings between new kerb and footpath edge
- Reinstatement of nature strips
- Total length 100m
Budget and Timelines
- Budget $195,000
- Construction Start Date: September 2019
- Construction End Date: December 2019