Cumming Street, Brunswick West - Road reconstruction works
Project overview
In 2019 Council reconstructed Cumming Street, Brunswick West between Melville Road and Duggan Street.
The works comprised:
- Construction of a new underground drainage system and pits.
- Reconstructing the existing bluestone kerb and channel.
- Reconstructing the existing road pavement.
- Construction of a tree lined median along the road.
- Laying of a new asphalt road surface.
- Reconstruction of vehicle crossings between the new kerb and footpath edge.
- Reinstatement of nature strips.
- Total length: 380 metres.
Budget and timelines
- Budget: $1,317,000
- Construction start date: December 2018
- Construction end date: July 2019