Mitchell Parade, Pascoe Vale South - Road reconstruction works
Project overview
In 2018 Council reconstructed Mitchell Parade, Pascoe Vale South between Reynard Street and Vaux Street.
The project was completed in December 2018.
The works comprised:
- Construction of a new underground drainage system and pits.
- Reconstructing the existing concrete kerb and channel.
- Reconstructing the existing road pavement.
- Laying of a new asphalt road surface.
- Reconstruction of vehicle crossings between the new kerb and footpath edge.
- Reinstatement of nature strips.
- Total length: 340 metres.
Budget and timelines
- Budget: $622,105
- Construction start date: August 2018
- Construction end date: December 2018