Laneway at rear of 21 - 55 Newman Street, Brunswick West - Reconstruction works
Project overview
In 2018-19 Council reconstructed the bluestone laneway at the rear of 21 - 55 Newman Street, Brunswick West between Straw Street and Wallace Street.
The project was completed in April 2019.
The works comprised:
- Reconstructing the existing concrete kerb and channel.
- Reconstructing the existing bluestone pavement.
- Total length: 230 metres
Budget and timelines
- Budget: $367,000
- Construction start date: November 2018
- Construction end date: April 2019