Franklin Street, Coburg - Road reconstruction works

 

 

Project overview

In 2018 Council reconstructed Franklin Street, Coburg between Rennie Street and Harding Street.

The project was completed in December 2018.

The works comprised:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing concrete kerb and channel.
  • Reconstructing the existing road pavement.
  • Laying of a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total length: 145 metres.

Budget and timelines

  • Budget: $290,000
  • Construction start date: September 2018
  • Construction end date: December 2018