Laneway between Gladstone Street, Younger Street and Bell Street, Coburg - Reconstruction works

Project overview

Council has reconstructed the bluestone laneway between Gladstone Street, Younger Street and Bell Street, Coburg.

The works comprised:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing bluestone pavement.
  • Total length: 230 metres.

Budget and timelines

  • Budget : $320,000.
  • Construction start date: October 2017
  • Construction end date: December 2017