Laneway between Gladstone Street, Younger Street and Bell Street, Coburg - Reconstruction works
Project overview
Council has reconstructed the bluestone laneway between Gladstone Street, Younger Street and Bell Street, Coburg.
The works comprised:
- Construction of a new underground drainage system and pits.
- Reconstructing the existing bluestone pavement.
- Total length: 230 metres.
Budget and timelines
- Budget : $320,000.
- Construction start date: October 2017
- Construction end date: December 2017