Laneway between Cliff Street and Hope Street, Brunswick - Reconstruction works
Project overview
Council has reconstructed the bluestone laneway between 26A-44 Cliff Street and 71-91 Hope Street, Brunswick.
The works comprised:
- Construction of a new underground drainage system and pits.
- Reconstruction the existing bluestone pavement on a porous concrete base.
- Total length: 280 m
Budget and timelines
- Budget: $340,000
- Construction start date: February 2018
- Construction end date: May 2018