Laneway between Cliff Street and Hope Street, Brunswick - Reconstruction works

Project overview

Council has reconstructed the bluestone laneway between 26A-44 Cliff Street and 71-91 Hope Street, Brunswick.

The works comprised:

  • Construction of a new underground drainage system and pits.
  • Reconstruction the existing bluestone pavement on a porous concrete base.
  • Total length: 280 m

Budget and timelines

  • Budget: $340,000
  • Construction start date: February 2018
  • Construction end date: May 2018