Council has completed reconstruction of Cole Crescent, Coburg between Harding Street and Grant Street.

The works comprised:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing concrete kerb and channel. The levels will be altered to flatten the road and improve vehicle access into properties.
  • Reconstruction of the road pavement and laying a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total Length: 190 metres.

Budget and timelines

  • Budget: $390,000
  • Construction start date: December 2017
  • Construction end date: February 2018