Sydney Road, Coburg - Streetscape improvements (Stage 1)

Sydney Road pavingProject overview

Council carried out a streetscape upgrade along Sydney Road, Coburg.

The scope of these works were limited to both sides of Sydney Road between Munro/Harding Streets and Bell Street.

Works undertaken included:

  • The upgrade of existing bluestone kerb and channels on both sides.
  • Feature stone paving at key pedestrian intersections.
  • Removal and upgrade of existing asphalt footpath pavement.
  • Upgrade of existing seating, bins, signage and bike hoop infrastructure.

To minimise disruption to the public, the majority of works were performed outside of business hours.  

Budget and timelines

  • Budget: Council funding $2,400,000
  • Construction of east Side starts 11 January 2017
  • Construction of west side to start March 2017 

Major stages of the project

Consultation - complete

Consultation was performed late 2016. This feedback was collated and used to inform the design and delivery of the Sydney Road upgrade. Once the upgrade is complete, a post survey will be sent out for feedback.  

The purpose of the pre and post construction surveys is to get community feedback to measure satisfaction in relation to streetscape improvements undertaken and inform future upgrades.

Tendering - complete

Public tender for the construction work was advertised in June 2016.

Construction 

Started 11 January 2017 and finished June 2017.

Enquiries

If you have an enquiry or would like further information about this project, please contact Council.