Gordon Street, Coburg - Road reconstruction works

Gordon Street before reconstructionProject overview

Council has completed the reconstruction of Gordon Street, Coburg between Bell Street and Munro Street.

The works comprised of the following:

  • Construction of a new underground drainage system and pits.
  • Installation of three speed humps to reduce speed and through traffic along the street.
  • Relaying the existing bluestone kerb and channel along the new alignment so as to flatten the road and improve vehicle access into properties.
  • Excavation of the existing road pavement and laying of a new asphalt road surface.
  • Reconstruction of vehicle crossings.
  • Total length: 390 metres.

Budget and timelines

  • Budget: $750,000
  • Construction began in March 2016
  • Construction completed in September 2016