Charles and Dawson Street, Coburg North - Roundabout construction

Project overview

Council has completed the construction of a roundabout at the intersection of Charles Street and Dawson Street, Coburg North.

The intersection of Charles Street and Dawson Street has had a history of vehicle crashes. Nation Building Blackspot funding was applied for and subsequently approved by VicRoads.

A rubber roundabout was installed at the site in February 2014 as a trial in order to ascertain if a roundabout would reduce crashes at the intersection. A subsequent assessment determined that the roundabout had reduced crashes at the intersection and therefore a permanent concrete roundabout and associated traffic islands were constructed at the site.

The works were undertaken by ADP Constructions Pty Ltd.

Budget and timelines

  • Budget: $110,215
  • Construction start date: January 2015
  • Construction end date: January 2015

Charles & Dawson Streets, North Coburg - Roundabout During Construction Charles and Dawson Streets, North Coburg - Roundabout During Construction 2

The roundabout during construction

Charles & Dawson Streets, North Coburg - Roundabout -   Works Completed Charles & Dawson Streets, North Coburg - Roundabout -   Works Complete 2

The completed roundabout

Enquiries

If you have an enquiry or would like further information about this project, please contact Council.