Dunnes Lane, Coburg - Pedestrian link

Dunnes LaneProject overview

Council has recently upgraded Dunnes Lane in Coburg. The purpose of this project was to improve the laneway's pedestrian accessibility and presentation.

Budget and timelines

  • Budget: Council funding $200,000 plus Melbourne Water Grant $42,500
  • Construction start April 2016

Major stages of the project

Consultation - complete

Consultation for this project finished in September 2015.

Design - complete

From the feedback Council received during the consultation process, a final design for Dunnes Lane was developed.

Tendering - complete

Public tender for the construction work was advertised over November - December 2015.

Construction - complete

Construction was completed in August 2016.